Published: Nov 7, 2026
Calculating...
COLOMBO, November 7, 2026: Sri Lanka’s Port of Colombo handled a record 8.29 million TEUs in 2025, but an audit of terminal equipment, exporters’ complaints and research on customs and digital trade point to operational challenges beyond the new capacity as the country pursues a wider maritime hub role.

The Sri Lanka Ports Authority (SLPA) recorded 8,291,178 twenty-foot equivalent units (TEUs) in 2025, compared with 7,792,069 TEUs in 2024. The Central Bank of Sri Lanka reported that the first phase of Colombo West International Terminal (CWIT) began operations in late February 2025 and that the additional capacity supported a recovery in port activity from May.

Business groups, however, raised concerns about congestion, vessel omissions and delays affecting exporters. In January last year, 29 chambers and trade associations called for an immediate action plan, citing delays to imported inputs, missed shipping opportunities and higher processing costs.

The competing records point to several parts of port performance that container throughput alone cannot measure: vessel calls, terminal equipment, cargo clearance and the reliability of services used by importers and exporters.

Congestion and stakeholder concerns

The Central Bank’s record showed that congestion affected operations during the first half of 2024 before easing in the third quarter. It also recorded a decline in ship arrivals, primarily because shipping lines deployed larger vessels. Port activity subsequently increased, with Colombo handling a record 8.29 million TEUs in 2025.

The joint chambers and associations said in January last year that delays at Colombo were affecting imported inputs, shipping opportunities and processing costs. Their proposed measures included round-the-clock scanning and screening, better coordination among border agencies, expanded use of the green channel, additional container-yard capacity and greater digitalisation of clearance procedures. The group also warned that reports of ships bypassing Colombo could affect the port’s transshipment business.

A letter from the FTZMA that appeared in local media in November last year raised a related concern. The association said frequent vessel omissions had disrupted supplies of raw materials for garment, rubber and electronics manufacturers, delayed production and put export deadlines at risk. It called for improvements in yard efficiency, inter-terminal transfers and road connectivity, alongside the commissioning of additional terminal capacity.

These concerns describe the experience of businesses relying on predictable cargo movement. They do not, by themselves, establish that every delay resulted from port congestion, but they show why record throughput cannot be treated as a complete measure of service reliability.

Terminal equipment and operating capacity

The Auditor General’s report on the Sri Lanka Ports Authority documented delays in putting equipment purchased for the Colombo East Container Terminal (CECT) into operation. The Authority had purchased 12 ship-to-shore cranes and 40 rail-mounted automated gantry cranes for US$282.56 million. Although all the cranes had been received by June 6, 2025, only six ship-to-shore cranes were being used. The remaining six and all 40 automated gantry cranes were idle because the Phase II reclamation area had not been completed.

The audit also found that attempts to procure straddle carriers had failed to progress despite four rounds of bidding since 2021. The equipment was intended to transfer containers between the crane yard and the container yard. The report attributed the delay to differences in decisions during the bidding process and the absence of a proper assessment of the required equipment, quantities and specifications.

The findings concern CECT rather than CWIT, and they show that adding equipment to a port does not automatically translate into operational capacity. The completion of supporting infrastructure, commissioning and procurement also affect how much of the installed capacity can be used.

Port competitiveness beyond container volumes

A 2024 study, “Beyond throughput: Evaluating maritime port competitiveness using MABAC and Bayesian methods”, assessed 20 major ports on the Asia-Europe service route using several criteria, including port processing time, bunker fuel quality and availability, geographical advantages and port security. Colombo ranked first among the ports included in that assessment.

Sri Lanka’s port ambitions face a test beyond terminal capacity
The ranking provides a broader measure than container throughput alone, but it is specific to the study’s selected route and criteria. It does not establish that Colombo leads across every shipping service or that the port’s operational and trade-facilitation problems have been resolved.

Research on the port’s digital development also points to areas requiring attention. A 2025 study on digitalisation and sustainability at Colombo Port found positive links between information and communications technology, safety and security, and port competitiveness. It also found that automation, connectivity and environmental management required further attention through infrastructure development, investment, governance, trading partnerships, legal frameworks and capacity building.

The findings place digital systems and supporting institutions alongside physical infrastructure as factors in port competitiveness. They also connect the port’s performance to the services and procedures that businesses encounter beyond the terminal gates.

Customs performance and the experience of traders

Sri Lanka Customs’ Time Release Study 2025 recorded an improvement in the median release time for sea imports, which fell to 51 hours and 32 minutes in 2025 from 54 hours and 19 minutes in 2024. The average release time also declined, from 83 hours and three minutes to 76 hours and 43 minutes. The study used data from 6,787 sea-import declarations in 2025 and noted that median times provide a more representative measure of routine clearance than averages affected by unusually long delays.

A separate ODI Global survey of 953 exporters and importers found that around 67 per cent of e-commerce traders considered customs delays a major barrier, while 80 per cent of businesses reported burdensome documentation requirements. The survey also found that 90 per cent of exporters relied mainly on manual bank transfers for cross-border payments and that international fulfilment and transit frequently took more than two weeks.

The two sources measure different aspects of trade facilitation. Customs’ study recorded an improvement in cargo release times, while the ODI Global survey captured wider business concerns involving documentation, payments and logistics. Together, they show that customs release time is only one part of the experience facing trading companies.

The commercial hub proposal

Sri Lanka’s port ambitions face a test beyond terminal capacity
Sri Lanka has a legal framework for activities beyond conventional container transshipment. The Export Development Board describes commercial hub operations under regulations introduced in 2013, covering entrepôt trade, offshore business, front-end services, headquarters operations and logistics. The framework also provides for designated free ports and bonded areas.

The Sri Lanka Customs entrepôt scheme allows goods to be imported and re-exported to a third country without payment of Sri Lankan customs duties and levies. Goods may be re-exported directly or held in bonded warehouses, with limited processing such as repacking and relabelling permitted under the scheme.

The Government also outlined a proposed management arrangement for the East Container Terminal in October this year. At the Sri Lanka Economic and Investment Summit, President Anura Kumara Dissanayake said the state would retain ownership while a management company would be established, with shares transferred to private investors. He also said the Government was in talks with several major shipping companies. 

The commercial hub framework and the proposed ECT management arrangement are separate parts of Sri Lanka’s wider port strategy. The framework establishes routes for trade and logistics services; the management proposal concerns how a major terminal would be run. The terms and implementation of the proposed arrangement remain to be set out.

Sami Ahmed, Editor, TradeTrend
About the Author
Sami Ahmed is a seasoned journalist with more than 30 years of experience in news agencies and newspapers. He is the Editor of TradeTrend and has extensively covered consulates, diplomatic affairs, bilateral relations, economy, trade and global geopolitical developments.